Quick Reference
10 min read
Every framework, formula and case from the five sessions, on one page
On this page 7 sections
Every item here is covered in more depth in Sessions 1 to 5.
Formulas
| Formula | What it gives | Worked number |
|---|---|---|
| Cycle time = time of the slowest stage | Gap between finished units | Collate 2 min, staple 1 min → 2 min |
| Capacity = (60 ÷ minutes per unit) × servers | Units per hour at a stage | 4 min, 5 counters → 75 an hour |
| Throughput time = operation + waiting | Time one unit spends inside | 2 + 1 = 3 min |
| Utilisation = output ÷ capacity | How busy a resource is | 7.5 ÷ 8.5 = 88% |
| Little’s Law: inventory = rate × time | Units in the system | 60 an hour × 1 hour = 60 |
| Inventory turns = sales ÷ average inventory | How fast stock moves | 1 ÷ 5 days |
| EOQ = √(2DS ÷ H), with H = rate × unit cost | Best order size | √(2 × 12,000 × 120 ÷ 2) = 1,200 |
| Cyclic stock = Q ÷ 2 | Average stock from ordering in lots | Buy every 30 days → 15 days |
| Safety stock = average inventory − Q ÷ 2 | The cushion | 25 − 15 = 10 days |
| Critical ratio = Cu ÷ (Cu + Co) | Target service level | 7.5 ÷ (7.5 + 2.5) = 0.75 → stock 70 |
| Pooled SD = √(SD₁² + SD₂² + 2r·SD₁·SD₂) | Noise after pooling | 3 and 4: r = −1 → 1; 0 → 5; +1 → 7 |
| Utilisation ρ = λ ÷ μ | Arrival rate over service rate | 9 ÷ 10 = 90% |
| Queue size L = ρ ÷ (1 − ρ) | Average number in the system | 90% → 9; 99% → 99 |
| Dumper cycle time = larger of loading time and round trip ÷ n | Output with n vehicles | 3 dumpers → 8.5 min. Three minimise cost per load (about ₹369); four finish soonest |
| Reorder point = demand × lead time | When to order | |
| Lowest yearly cost at the EOQ = √(2DSH) | Ordering cost equals holding cost there |
Ten lines that carry the module
- Every operations design takes its mandate from the differentiation strategy. Fit beats best practice.
- Being off the benchmarking curve is the crime. The level of value you choose is your own business.
- A disruption removes an accepted trade-off, at scale.
- Process moats (Zara, Toyota, Dell) outlast product moats (Apple, Nokia), because culture can’t be copied.
- Efficiency is doing things right; effectiveness is doing the right things. Design for both.
- Inventory follows variability and the service level, not volume.
- Grade the fit of outsourcing to what you compete on, never the level. Outsource tasks, never capabilities.
- Pooling is a dial, not a doctrine, set by whatever your differentiation makes expensive.
- High utilisation under variability is a crime. Turning demand away kills sales, so add capacity.
- Buffers aren’t waste when variability is real. Resilience is measured slack.
Frameworks
| Framework | In one line |
|---|---|
| Strategy cascade | Corporate (which game) → business (how to win) → functional (how to deliver) |
| De-risking vs decoupling | Diversify supply vs rebuild capability at home |
| Benchmarking curve | Below the frontier is waste: cut cost for the same value, or add value for the same cost |
| V = C × (A + P) | Value = capabilities × (assets + processes). Assets: sizing, timing, type, location |
| Product vs process innovation | Product advantages are visible and copied; process advantages last |
| Input vs resource | After the transformation, the input is gone and the resource remains |
| Efficiency | Minimum cost per unit of output; serves the owner |
| Effectiveness | Maximum welfare (value minus price) for every other stakeholder |
| Operational excellence | Efficiency + effectiveness, by design |
| Five process types | Job shop, batch, assembly line, continuous flow, project |
| MTS, MTO, ATO | Make to stock, make to order, or stock a base and finish to order |
| ABC analysis | A: 10% of items, 70% of value. Small frequent lots, most safety stock |
| Kraljic matrix | Value × supply risk: leverage, strategic, routine, bottleneck |
| Three costs, two trade-offs | Ordering vs holding (cyclic stock); holding vs shortage (safety stock) |
| OS vs OM | Design the system vs run the system |
| Make or buy | Judge the fit with what you compete on, not the level of outsourcing |
| Product–process matrix | Variety must be matched by flexibility; stay on the diagonal |
| Risk pooling | Combining demands cuts noise, at the cost of lead time |
| Lean | Remove waste; empower people; build long-term supplier trust |
| Hold-up problem | Sunk investment plus unverifiable forecasts; fix with shared investment or contract menus |
Easy to confuse
| If you see… | Remember… |
|---|---|
| Cycle time | The gap between finished units, not the time one unit spends inside |
| Manpower | A resource, not an input |
| Bottleneck | The limiting stage in a process. “Critical path” belongs to project management |
| Assembly line | Any repetitive process, including sandwiches and surgery |
| Which system has the longer lead time | Total: make-to-stock. Felt by the customer: make-to-order |
| A items | Ordered often in small lots, but with the most safety stock. C items: bulk, and forget |
| “Make-to-order is better because inventory is zero” | It trades inventory for the customer’s wait and for idle capacity. Make-to-stock serves about 95% of the market for a reason |
| “Dell is flexible” or “Dell is rigid” | Dell is on the diagonal: a standard 70–80%, a customised final slice |
| “Benchmark against the industry leader” | Only within your own diagonal |
| “Cheaper AI units will shrink the AI bill” | The bill is cost × number of calls, and the number is exploding |
| Shortage cost | Lost profit, invisible in the accounts |
| “High demand needs high inventory” | False if demand is predictable. Variability drives stock |
| Vertical integration | Neither good nor bad. It buys control; ask whether control is what you need |
| DMart | Fast payment is the symptom; the curated range is the cause |
| Pooling | Can never increase risk, but always costs lead time |
| Inventory turns | Reflect the business model. Compare only like with like |
| High utilisation | Fine for predictable work; a recipe for queues when work is variable |
| Lean | Not zero slack. Slack is what absorbs variability |
One toolkit, two worlds
| Idea | In a product business | In a service business |
|---|---|---|
| Bottleneck and cycle time | The slowest machine on the packing line caps the plant | The one X-ray room caps the outpatient clinic; check-in capped the class’s airport at 75 an hour |
| Make-to-stock and make-to-order | Soap is made to stock; a ship or a wedding outfit is made to order | A buffet is made to stock; à la carte is made to order; managed IT services run a standard catalogue with project work on top |
| Safety stock | A national oil reserve; thin buffers on predictable staples | Extra cross-trained nurses on weekend shifts; standby aircraft, which a low-cost airline chooses not to keep |
| EOQ thinking | Lot sizes for flour at a kirana or components at a car plant | How often a cash machine is refilled: the cost of a visit against the cost of idle cash |
| Newsvendor | Newspaper print runs, bakery output, fashion buys | Overbooking seats on a flight; staffing a call centre for an uncertain Monday |
| Risk pooling | One regional warehouse replacing five city depots | One queue feeding all tellers; reallocating crews from a hub after a storm |
| Product–process matrix | Ford far to the narrow side; a marketplace far to the wide side; Dell on the diagonal | A focused heart hospital on the narrow side; a multi-speciality hospital on the wide side |
| Lean | Suppliers within a few kilometres, delivering three or four times a day | A coffee made in 40 seconds, not 60; online tax filing cutting the cost of collection |
| The queueing law | Work piling up before a machine as utilisation nears 100% | An airline at 99% utilisation, where one rostering shock brings the system down |
Which company illustrates what
| Company | Use it for |
|---|---|
| IndiGo | One strategic choice shaping the whole design; standardisation concentrating risk; no slack for shocks |
| Zara | Speed through an owned supply chain; small lots; effective rather than efficient |
| Toyota | Lean; culture as part of the process; efficient and effective; patience on electric vehicles |
| Apple | Product-led advantage; narrow range and high inventory turns |
| Dell | Assemble-to-order; mass customisation on the diagonal |
| Lemon Tree | Effectiveness that pays for itself |
| Aravind Eye Care / a focused heart hospital | Assembly-line discipline producing quality at low cost |
| Asian Paints | Customisation pushed out to the dealer |
| Intel | Too much vertical integration when value moved outside |
| Boeing | Outsourcing the thing it competes on: quality control |
| DMart | Low variability → low inventory → the flywheel |
| Amazon | Un-pooling on purpose to win on speed |
| Netflix | Pooled warehouses removing a trade-off |
| FedEx | Pooling two networks when their demands diverged |
| Southwest | Point-to-point: strong against local shocks, slow to recover from large ones |
| GM | Copying lean’s checklist without its culture |
The module in one sentence
Firms don’t fail for choosing cost, speed or variety. They fail for running an operations design that contradicts the promise they made to the customer.
A closing word
Take a second to notice what you now carry. You can read any business as a process and find its bottleneck in minutes. You can tell efficiency from effectiveness, and explain why the firms that design for both quietly out-earn the ones that squeeze. You know why the world makes to stock, what a ten-minute delivery really costs, and how to split any inventory into cyclic and safety stock. You can diagnose Intel and Boeing from opposite ends of the same mistake, run the DMart flywheel forwards and backwards, set the pooling dial, and see the arithmetic behind an airline’s worst December.
Every question about an operation is one of six moves: classify the process, name the clock, find the bottleneck, run a formula, grade a fit, or spot a flip. And keep the habit both professors kept pointing at: once a week, walk through a process and ask “is there some other way to do this?” That is where careers get made.